What are you likely to see as a project progresses in a schedule with must fix dates and little or n admin 11 years ago What are you likely to see as a project progresses in a schedule with must fix dates and little or no slack? A.Idle resources B.Negative float C.Lots of free float D.Positive float ← Previous question Next question →