What are you likely to see as a project progresses in a schedule with must fix dates and little or n seenagape 9 years ago What are you likely to see as a project progresses in a schedule with must fix dates and little or no slack? A.Lots of free float B.Idle resources C.Negative float D.Positive float ← Previous question Next question →