To-complete performance index (TCPI) is represented by which of the following?

To-complete performance index (TCPI) is represented by which of the following?

A.
BAC – EV/BAC – AC

B.
A measure of the value of work completed compared to the actual cost or progress

C.
A measure of progress achieved compared to progress planned

D.
AC + (BAC – EV)