A project team attempts to produce a deliverable and finds that they have neither the expertise nor the time to
complete the deliverable in a timely manner. This issue could have been avoided if they had created and
followed a:

A.
risk management plan
B.
human resource management plan
C.
scope management plan
D.
procurement management plan