This is an example of which type of risk response strategy?

The project manager decides to conduct a meeting with the team and management after a new risk has been identified. After the meeting, the decision is to allow the risk to occur.

This is an example of which type of risk response strategy?

A.
Mitigate

B.
Accept

C.
Avoid

D.
Transfer