This is an example of which of the following?

You are the project manager for a Project. Project is a global project. Some peoples are working from US and some are from India. Client says budget should not cost more than $12 million. Because of the global concerns, the final budget must be in U.S. dollars. This is an example of which of the following?

A.
Internationalization

B.
Budget constraint

C.
Management constraint

D.
Quality constraint

Explanation:
This is an example of a budget constraint. The budget must not exceed $12 million.