A forward and backward pass indicted total float is equal to – 30 days. This indicates that:
A.
The critical path must be evaluated to determine actual slack time.
B.
The project is estimated to be-20 days ahead of schedule.
C.
Two branches converge on a node.
D.
Duration compression may be required to meet the original project scope.