PMI Exam Questions

This indicates that:

A forward and backward pass indicted total float is equal to – 30 days. This indicates that:

A.
The critical path must be evaluated to determine actual slack time.

B.
The project is estimated to be-20 days ahead of schedule.

C.
Two branches converge on a node.

D.
Duration compression may be required to meet the original project scope.