A project team member agrees to change a project deliverable after a conversation
with an external stakeholder.It is later discovered that the change has had an
adverse effect on another deliverable. This could have been avoided if the project
team had implemented:

A.
Quality assurance.
B.
A stakeholder management plan.
C.
Project team building.
D.
Integrated change control.