The Verify Scope process is primarily concerned with:

The Verify Scope process is primarily concerned with:

A.
formalizing acceptance of the completed project deliverables.

B.
accuracy of the work deliverables.

C.
formalizing approval of the scope statement.

D.
accuracy of the work breakdown structure (WBS).