The velocity chart, storyboard, burndown chart, and impediment list are often communicated using: seenagape 9 years ago The velocity chart, storyboard, burndown chart, and impediment list are often communicatedusing: A. Project data packages. B. Status reports. C. Information radiators. D. Portfolio presentations. ← Previous question Next question →