The technique of subdividing project deliverables into … seenagape 8 years ago The technique of subdividing project deliverables into smaller, more manageable components until the workand deliverables are defined to the work package level is called: A. a control chart. B. baseline. C. Create WBS. D. decomposition. ← Previous question Next question →