The __________ task relationship is defined by the activity duration:

The __________ task relationship is defined by the activity duration:

A.
Start-to-start

B.
Finish-to-finish

C.
Start-to-finish

D.
None of the above

Explanation:
All the above relationship is defined by Sequence Activities