PMI Exam Questions

The solution reached during the initial project meeting is a result of which of the following confli

During your project meeting, a problem was discussed, and a resolution to the problem was reached. During the meeting, the participants started wondering why they thought the problem was such a big issue. Sometime after the meeting, you received an email from one of the meeting participants saying they’ve changed their mind about the solution reached in the meeting and need to resurface the problem. The solution reached during the initial project meeting is a result of which of the following conflict resolution techniques?

A.
Forcing

B.
Confrontation

C.
Storming

D.
Smoothing

Explanation:
The smoothing technique does not usually result in a permanent solution. The problem is downplayed to make it seem less important than it is, which makes the problem tend to resurface later.