The purpose of a project burndown chart is to:

The purpose of a project burndown chart is to:

A.
Identify and communicate upcoming milestones.

B.
Display the level of effort and resources utilized.

C.
Identify dependencies between sprints or iterations.

D.
Display the remaining work across time.