The project manager’s leadership style should be matched to the corresponding developmental level of the project team and should move through successive steps in the following order:
A.
Disciplinary, autocratic, and participative
B.
Staff planning, team training, and performance monitoring
C.
Team building, team development, and responsibility assignment
D.
Directing, coaching, supporting, and delegating