A project manager believes that modifying the scope of the project may provide added value for the customer. The project manager should:
A.
Change the project’s objectives
B.
Call a meeting of the configuration control board
C.
Postpone the modification until a separate enhancement project is funded after this project is completed according to the original baseline
D.
Change the scope baseline
E.
Prepare a variance report