The project management processes presented in the PMBOK… seenagape 8 years ago The project management processes presented in the PMBOK Guide® should: A. always be applied uniformly. B. be selected as appropriate by the sponsor. C. be selected as appropriate by the project team. D. be applied based on ISO guidelines. ← Previous question Next question →