PMI Exam Questions

The Project Human Resource Management process that involves confirming human resource availability a

The Project Human Resource Management process that involves confirming human resource
availability and obtaining the team necessary to complete project activities is:

A.
Acquire Project Team.

B.
Plan Human Resource Management.

C.
Manage Project Team.

D.
Develop Project Team.