The process that is not a part of time management is:

The process that is not a part of time management is:

A.
Define Activities

B.
Resource Planning

C.
Develop Schedule

D.
Sequence Activities

Explanation:
Time management includes : Define Activities, Sequence Activities, Estimate Activity Durations, Develop Schedule and Control Schedule