The process of prioritizing risks for further analysis or action is known as: seenagape 9 years ago The process of prioritizing risks for further analysis or action is known as: A. Plan Risk Management. B. Plan Risk Responses. C. Perform Qualitative Risk Analysis. D. Perform Quantitative Risk Analysis. ← Previous question Next question →