PMI Exam Questions

The process of monitoring the status of the project to update project progress and manage changes to

The process of monitoring the status of the project to update project progress and manage
changes to the schedule baseline is:

A.
Control Schedule.

B.
Quality Control.

C.
Perform Integrated Change Control.

D.
Develop Schedule.