The process of Manage Stakeholder Expectations is part of which process?

The process of Manage Stakeholder Expectations is part of which process?

A.
Executing

B.
Monitoring and Control

C.
Planning

D.
QA

Explanation:
Manage Stakeholder Expectations is part of Monitoring and Control process.