PMI Exam Questions

The process of identifying and documenting the specific…

The process of identifying and documenting the specific actions to be performed to produce the project
deliverables is known as:

A.
Define Activities.

B.
Sequence Activities.

C.
Define Scope.

D.
Control Schedule.