The process of identifying and documenting relationships among the project activities is known as: seenagape 9 years ago The process of identifying and documenting relationships among the project activities is known as: A.Control Schedule. B.Sequence Activities. C.Define Activities. D.Develop Schedule. ← Previous question Next question →