The process of identifying and documenting relationships among the project activities is known as: seenagape 9 years ago The process of identifying and documenting relationships among the projectactivities is known as: A. Control Schedule. B. Sequence Activities. C. Define Activities. D. Develop Schedule. ← Previous question Next question →