PMI Exam Questions

The process of confirming human resource availability and obtaining the team necessary to complete p

The process of confirming human resource availability and obtaining the team necessary to
complete project activities is known as:

A.
Plan Human Resource Management.

B.
Acquire Project Team.

C.
Manage Project Team.

D.
Develop Project Team.