PMI Exam Questions

The Process Group that involves coordinating people and resources…

The Process Group that involves coordinating people and resources, as well as
integrating and performing the activities of the project in accordance with the
project management plan is known as:

A.
Initiating.

B.
Planning.

C.
Executing.

D.
Monitoring and Controlling.