The probability and impact matrix is primarily used to:

A.
Quantify risk issues for trends during a quality audit.
B.
Develop a risk register for risk planning.
C.
Evaluate each risk’s importance and priority during Perform Qualitative Risk Analysis.
D.
Define risk and compare impacts during Perform Quantitative Risk Analysis.