The highest degrees of project risk and uncertainty are associated with the following phase of the p admin 11 years ago The highest degrees of project risk and uncertainty are associated with the following phase of the project: A.Both 1) conceptual, and 2)post project evaluation B.cut-over C.conceptual D.execution E.post project evaluation ← Previous question Next question →