PMI Exam Questions

The highest degrees of project risk and uncertainty are associated with the following phase of the p

The highest degrees of project risk and uncertainty are associated with the following phase of the project:

A.
Both 1) conceptual, and 2)post project evaluation

B.
cut-over

C.
conceptual

D.
execution

E.
post project evaluation