The following reports are normally developed during the project closure phase?

The following reports are normally developed during the project closure phase?

A.
None of the other alternatives apply

B.
Communications Management Plan and Lessons Learned

C.
Records Archive, Closure Report, & Specifications Document

D.
Records Archive, Closure Report, lessons learned & Formal Acceptance Report

E.
Communications Management Plan and Closure report