The erection of foundation formwork before the placement of foundation concrete would be an example

The erection of foundation formwork before the placement of foundation concrete would be an example of a _____ dependency.

A.
Soft logic

B.
Subcontracted

C.
Mandatory

D.
Discretionary

E.
External