The engagement level of the stakeholders should be clas…

The project manager notes that stakeholders are aware of the project and potential impacts and are actively
engaged in ensuring that the project is a success. The engagement level of the stakeholders should be
classified as:

A.
Supportive

B.
Leading

C.
Neutral

D.
Resistant