The critical path in a schedule network is the path that:

The critical path in a schedule network is the path that:

A.
Takes the longest time to complete

B.
Allows some flexibility in scheduling a start time.

C.
Is not affected by schedule slippage

D.
Must be done before any other tasks

E.
All of the other alternatives apply.