PMI Exam Questions

The Collect Requirements process is:

The Collect Requirements process is:

A.
Developing a plan from major stakeholders

B.
Developing a written scope statement as the basis for future project decisions

C.
Formalizing acceptance of the project scope

D.
Planning project milestones

Explanation:
Collect Requirements :Process of progressively elaborating and documenting the project work that produces the product of the project