The business needs, assumptions, and constraints and the understanding of the customers needs and hi

The business needs, assumptions, and constraints and the understanding of the customers needs
and high-level requirements are documented in the:

A.
Project management plan.

B.
Project charter.

C.
Work breakdown structure.

D.
Stakeholder register.