PMI Exam Questions

The basis of identification for current or potential problems to support later claims or new procure

The basis of identification for current or potential problems to support later claims
or new procurements is provided by:

A.
A risk urgency assessment.

B.
The scope baseline.

C.
Work performance information.

D.
Procurement audits.