The ability to achieve cost savings is inversely proportional to _____.

The ability to achieve cost savings is inversely proportional to _____.

A.
empowerment to the P.M.

B.
productivity

C.
the estimated costs to complete

D.
the earned value achieved to date

E.
None of the other alternatives apply