PMI Exam Questions

[tagged] After program closure, the lessons learned document becomes the part of ____?

[tagged]
After program closure, the lessons learned document becomes the part of ____?

A.
The risk register

B.
The company’s organizational process assets

C.
The program’s performance record

D.
The program charter