PMI Exam Questions

Status of deliverables, implementation status for change requests, and forecasted estimates to compl

Status of deliverables, implementation status for change requests, and forecasted
estimates to complete are examples of:

A.
Earned value management.

B.
Enterprise environmental factors.

C.
Organizational process assets.

D.
Work performance information.