Risk mitigation includes all but which of the following:

Risk mitigation includes all but which of the following:

A.
performing contingent planning

B.
Obtaining insurance against loss

C.
Developing system (policies, procedures, responsibilities)

D.
identification of project risks.

E.
developing planning alternatives