RFP (Request for proposal) is done in _______.

You are project manager and now in middle of creating RFP (Request for proposal). RFP (Request for proposal) is done in _______.

A.
Plan Procurements

B.
Conduct Procurements

C.
Administer Procurements

D.
Close Procurements

Explanation:
RFP (Request for proposal) is done in Plan Procurements process.