Reserve Analysis a technique not used in:
A.
Estimate Costs
B.
Estimating Activity Duration
C.
Control Costs
D.
Determine Budget
Explanation:
Reserve Analysis: Many cost estimators include reserves, also called contingency allowances, as costs in many schedule activity cost estimates. Reserve Analysis a technique not used in Control Costs.