Reserve Analysis a technique not used in:

Reserve Analysis a technique not used in:

A.
Estimate Costs

B.
Estimating Activity Duration

C.
Control Costs

D.
Determine Budget

Explanation:
Reserve Analysis: Many cost estimators include reserves, also called contingency allowances, as costs in many schedule activity cost estimates. Reserve Analysis a technique not used in Control Costs.