Providing forecasts to update current cost and schedule information is a part of which process?

Providing forecasts to update current cost and schedule information is a part of which process?

A.
Perform Integrated Change Control

B.
Direct and Manage Project Execution

C.
Monitor and Control Risks

D.
Monitor and Control Project Work