Project Risk Management includes all of the following processes EXCEPT ________.

Project Risk Management includes all of the following processes EXCEPT ________.

A.
Plan Risk Management

B.
Identify Risks

C.
Risk Analysis

D.
Plan Response

Explanation:
Perform qualitative risk analysis and Perform quantitative risk analysis is the process of Project Risk Management NOT Risk Analysis