Project Risk Management includes all of the following processes EXCEPT ________.
A.
Plan Risk Management
B.
Identify Risks
C.
Risk Analysis
D.
Plan Response
Explanation:
Perform qualitative risk analysis and Perform quantitative risk analysis is the process of Project Risk Management NOT Risk Analysis