Project Managers have maximum authority in which type of organization?

Project Managers have maximum authority in which type of organization?

A.
Weak Matrix organization

B.
Strong Matrix

C.
Balanced Matrix organization

D.
None

Explanation:
Weak Matrix : Power reset with Functional Manager.
Strong Matrix: Power rest with Project Manager.
Balanced Matrix :Power is shared between both Functional and Project Manager.