Planning activities such that predetermined resource availability pools are not exceeded is called:

Planning activities such that predetermined resource availability pools are not exceeded is called:

A.
Manpower planning.

B.
Manpower leveling.

C.
Resource leveling.

D.
Manpower contingency planning.

E.
Resource limited planning.