Planning activities such that predetermined resource availability pools are not exceeded is called: admin 11 years ago Planning activities such that predetermined resource availability pools are not exceeded is called: A.Manpower planning. B.Manpower leveling. C.Resource leveling. D.Manpower contingency planning. E.Resource limited planning. ← Previous question Next question →