Perform Integrated Change Control is the process of:

A.
Reviewing, approving, and managing all change requests
B.
Facilitating change management, manuals, or automation tools
C.
Comparing actual results with planned results in order to expand or change a project
D.
Documenting changes according to the change control system by the change control board