PMI Exam Questions

Parametric Estimating is done as a part of which of the following process:

Parametric Estimating is done as a part of which of the following process:

A.
Develop Schedule

B.
Estimate Activity Durations

C.
Sequence Activities

D.
Estimate Activity Resources

Explanation:
Tools and Techniques for Estimate Activity Durations are : Analogous estimates , Parametric Estimating, Three-Point Estimates and Reserve Analysis.