PMI Exam Questions

Outputs of the Control Communications process include:

Outputs of the Control Communications process include:

A.
expert judgment and change requests.

B.
work performance information and change requests.

C.
organizational process asset updates and an issue log.

D.
project management plan updates and an issue log.