Life cycle costing __________________.

Life cycle costing __________________.

A.
Includes acquisition, operating, and disposal costs when evaluating various alternatives

B.
Includes only the cost of the development or acquisition of a product or service

C.
Does not take into consideration the effect of project decisions on the cost of using the resulting product

D.
Botn B and c are correct